NACC Construction Updates (as of March 13, 2026):

Building (Community Center and Temple)

  • The building exterior is 100% complete.
  • Rough-in work for electrical and plumbing is complete and has passed inspection.
  • Framing is complete.
  • Temporary power has been connected. All work required for permanent power, including mains, meters, and transformers, has been installed. We are currently waiting for the county’s final approval to connect permanent power.
  • HVAC ductwork and system installation are complete. Work is currently underway on ceiling ducts and returns.
  • Roof replacement for the old building is complete.
  • Insulation and drywall installation are complete.
  • Ceiling grid and LED lighting are complete in the Community Center on all floors. Work is in progress in the lobby and temple areas.
  • Painting: Primer and the first coat have been completed. Final paint will begin after ceiling closure.
  • Fire sprinkler and fire alarm systems are installed. Work is currently underway to drop sprinkler heads through the ceiling.
  • New stair rail installation is complete.
  • Flooring materials for hallways, rooms, the party hall, main lobby, and temple have been selected. Installation will begin after ceiling closure and completion of the final paint.

Security System and Internet:

  • The security alarm system installation is complete.
  • The system includes alarms, live monitoring, and sensors at all doors and windows, along with motion sensors at various locations.
  • 12 security cameras with an NVR system have been installed. Additional cameras will be installed after construction is completed.
  • Internet and Wi-Fi service for the building is connected.

Murti and Woodwork:

  • All Murtis and woodwork, including doors, window framing, Tudal, and Aakhi Jhyal, have been manufactured and packaged.
  • These items are ready to be shipped but are currently on hold due to the recent conflict in the Middle East.

RV Purchase:

  • An RV home has been purchased and installed at the NACC premises. It is currently serving as a residence for Guru Ji.

Next Steps (In Sequence):

  1. Turn on permanent power and activate the HVAC system (after receiving county approval).
  2. Conduct water sprinkler system testing (planned for next week).
  3. Ceiling closure (after permanent power activation and successful sprinkler testing).
  4. Final painting.
  5. Flooring and trim installation.
  6. Installation of bathroom cabinets, toilets, vanities, and faucets.
  7. Installation of kitchen appliances.
  8. Exterior elevation finishing.

Project Timeline and Schedule

Reasons for Construction Delays:

  • Freezing temperatures during December and January.
  • County inspection and approval delays.
  • NOVEC, the building’s power company, identified during its final inspection that both existing transformers were outdated and needed replacement. They agreed to replace them at their cost because it fell under their scope of work.

We learned about this issue approximately four months ago. Addressing it required a lengthy administrative process involving the county, NOVEC, engineers, and contractors. Additional contractor work was required for underground electrical connections and construction of a concrete platform for the new transformers.

All necessary work has now been completed, including installation of brand-new transformers. We are currently waiting for county approval to connect permanent power.

Without permanent power, we cannot activate the air conditioning units, and without HVAC operation we cannot complete the ceiling closure process. Final painting and flooring installation can only proceed after the ceiling is closed.

There were also some delays from contractors and engineers at various stages of the project.

Expected Construction Completion:
Target completion is by the end of May, depending on the following factors:

  • County approval for permanent power connection
  • Completion of elevator installation
  • County final inspection and occupancy approval

Upcoming Organizational Timeline

  • AGM (Annual General Meeting): Scheduled for June, as required by the bylaws.
  • Election Timeline: Must be conducted within 90 days after receiving the occupancy permit (as per bylaws). The goal is to hold the election before the AGM.
  • Opening Day: Expected sometime in June.
  • Saptah and Fundraising Event: Proposed for late summer.

The executive team is continuously following up with the contractor, bank, and subcontractors to ensure steady progress. We will continue to keep everyone informed with regular updates.

We thank all our members, volunteers, and supporters for their continued patience and support throughout this process. We look forward to opening our own community center and temple very soon.